CDC vs DA: A Guide to NSW Approvals and BASIX for Your New Home

Building TipsBuildTec Homes24 Nov 2026

Before any new home in NSW can be built, it needs planning approval through one of two pathways. A Complying Development Certificate (CDC) is a fast-track approval for designs that meet a fixed set of state rules, while a Development Application (DA) is assessed by your local council on its merits and allows more design flexibility. Both pathways also need a BASIX certificate, which sets the energy, water and thermal performance your home has to meet.

Weighing up CDC vs DA comes down to your block, your design and how much flexibility you need. This guide explains how each approval works, how long they take, where BASIX fits in, and how to work out which pathway suits your build.

CDC vs DA at a glance

 

Complying Development Certificate (CDC)

Development Application (DA)

Who approves it

A registered certifier or your local council

Your local council (the consent authority)

What it is assessed against

Fixed standards in the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008

Your council’s Local Environmental Plan (LEP), Development Control Plan (DCP) and the zoning of your land

Number of steps

One. Planning and construction approval are combined

Two. DA consent first, then a Construction Certificate

Statutory timeframe

20 days for a new home in most established Sydney suburbs

40-day assessment period, with an average determination time of 70 days

Design flexibility

Low. The design must meet every standard

Higher. Council can consider variations to certain controls

Neighbours

Notified, but cannot make a submission

May be notified and can make submissions, depending on the project

BASIX certificate needed

Yes, for a new home

Yes, for a new home

What is a CDC?

A Complying Development Certificate is a single, combined planning and construction approval for straightforward residential projects. The NSW Government describes complying development as a fast-track assessment that can be determined by a council or a certifier. Because a CDC covers construction as well as planning, you don’t need a separate Construction Certificate before work starts.

What a CDC is assessed against

To qualify for a CDC, your project must comply with the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, often called the Codes SEPP. For a new one or two-storey home, the relevant rules sit in the Housing Code, which applies in the R1, R2, R3, R4 and RU5 zones.

These standards set firm limits on design elements such as:

  • building height, with a maximum of 8.5 m under the Housing Code
  • front, side and rear setbacks
  • landscaped area
  • site coverage and floor area
  • lot size and width, with a minimum lot area of 200 m2 and a minimum width of 6 m at the building line

There’s no room to negotiate under the current rules. If one standard isn’t met, the project can’t be approved as complying development. The NSW Government has exhibited proposed reforms that would allow some minor variations within the CDC pathway, so it’s worth checking where these land before you lodge.

When a CDC can't be used

Some land is excluded from complying development altogether, however well the design fits the standards. Common exclusions include:

  • heritage items and heritage conservation areas
  • environmentally sensitive land
  • bushfire-prone land rated BAL-40 or BAL-FZ (Flame Zone)
  • certain coastal hazard and acid sulphate soils land

Flood-prone lots aren’t automatically excluded, but extra standards apply. Your block’s planning certificate and a site assessment will show which of these, if any, affect your land.

Single storey home design facade with a double garage, suited to a CDC or DA approval in Sydney

What is a DA?

A Development Application is a request to your local council for development consent. Council assesses the proposal on its merits, which gives you more scope for a design that sits outside the standard CDC rules.

How council assesses a DA

A DA assesses your proposed home against the Development Control Plan (DCP) specific to your local council, as well as any other controls tied to the zoning of your land. Council also considers the likely impacts of the development, the suitability of the site, submissions from neighbours and the public interest. These matters are set out in section 4.15 of the Environmental Planning and Assessment Act.

A DA can offer greater design flexibility because it doesn’t have to meet the strict CDC standards. Council can consider variations to certain controls when they’re well justified, which suits custom designs, sloping or irregular blocks, and sites with heritage or environmental constraints.

The second step: your Construction Certificate

A DA is a two-step process. Once your DA is approved, you need a Construction Certificate (CC) before construction can begin. The CC confirms your detailed construction plans meet the Building Code of Australia and the conditions of your DA consent, and it can be issued by your council or a registered certifier.

With either pathway, you’ll also appoint a principal certifier (PA), who carries out the mandatory inspections during the build and issues the occupation certificate (OC) at the end.

How long does each approval take?

A DA is generally a longer process than a CDC. Under the Environmental Planning and Assessment Regulation 2021, the standard DA assessment period is 40 days, and the clock stops whenever council asks for more information. In practice it often takes longer, and the NSW Government puts the average DA determination time at 70 days. After that, you still need your Construction Certificate.

A CDC for a new home in most established Sydney suburbs has a 20-day determination timeframe, giving time for neighbours to be notified first. Because the CDC already covers construction, there’s no second approval to wait on.

What neighbours are told

Neighbours are notified under both pathways, but in different ways. For a CDC, the certifier or council must tell neighbours within 20 metres 14 days before the certificate can be approved. Neighbours can’t make a submission on a CDC. Once it’s issued, they must also be given at least 7 days’ notice before work starts in metropolitan areas.

For a DA, neighbours may be notified and can make submissions, which council has to consider. Since 1 September 2026, a statewide Community Participation Plan sets the exhibition rules for DAs, and some single dwellings of up to two storeys no longer need public exhibition. Councils can still choose to notify neighbours, so check how your council handles it.

Where BASIX fits in

BASIX, the Building Sustainability Index, sets minimum standards for water use, energy use and thermal comfort, and requires a report on the embodied emissions of your building materials. Every new home in NSW needs a BASIX certificate, whichever approval pathway you take.

What BASIX covers

Your BASIX assessment scores the design against targets in three main areas:

  • Water. Fixtures, rainwater tanks and landscaping that reduce mains water use.
  • Energy. Hot water systems, heating and cooling, lighting and any solar panels.
  • Thermal performance. How well the home holds a comfortable temperature, based on insulation, glazing, orientation and construction.

The BASIX standards increased on 1 October 2023. Thermal performance moved to the equivalent of a 7-star NatHERS rating, energy targets rose, and a new materials index began reporting embodied emissions. If you’ve seen older advice about BASIX, it may predate these changes.

When you'll need your BASIX certificate

The BASIX certificate is generated online through the NSW Planning Portal once the design meets every target. It’s then submitted with your DA or CDC application, and for a DA it’s also attached to your Construction Certificate application. The commitments in the certificate, such as the size of a rainwater tank or the type of glazing, need to be shown on your plans.

Timing matters. A BASIX certificate is valid for 3 months before it’s lodged, and if the design changes, the certificate needs to be updated to match.

How BASIX shapes your design

BASIX targets can affect window sizes and placement, insulation levels, the hot water system and whether you need a rainwater tank. Working these in during the design stage keeps your plans and your certificate aligned, rather than reworking drawings after the assessment comes back.

Contemporary two storey home facade with large glazing designed to meet BASIX certificate targets

CDC or DA: which pathway suits your block?

You can’t simply choose your approval pathway. Your block, zoning, design, site constraints and the planning controls that apply to your land all decide which options are open to you. Working through these questions gives you a good starting point:

  1. What is your land zoned? The Housing Code only applies in certain residential zones. Acreage and rural-zoned blocks are assessed under different rules.
  2. Are there land exclusions? Heritage listings, environmentally sensitive land and BAL-40 or BAL-FZ bushfire ratings rule out a CDC.
  3. Does the lot meet the minimums? Check the lot area, width at the building line and any access handle for battle-axe blocks.
  4. Can your design meet every standard? If you want a taller home, a larger footprint or reduced setbacks, a DA may be the better fit.
  5. How important is timing? If your site and design qualify, a CDC usually reaches approval faster.

If the answers point to a CDC but you’d have to compromise on the home you want, a DA can be worth the extra time.

What about knockdown rebuilds?

A knockdown rebuild goes through the same CDC or DA decision as any new home, with demolition of the existing house included in the approval. The same site checks apply, so an older suburb with a heritage conservation area, or a narrow block, may need a DA even when the new home is simple. You’ll also need supporting reports such as a contour survey, and in some cases bushfire, flood or dilapidation reports. Our guide on what to know before a knockdown rebuild covers the wider process.

How we choose the approval pathway at BuildTec Homes

We assess your block, zoning, design and site constraints during our preliminary design process, so we can advise on the best approval pathway early and make sure your design complies with the relevant requirements. Getting this right at the start avoids redesigns later.

As part of our process, the pre-construction stage includes:

  • a site inspection, contour survey and borehole report
  • preliminary plans for your home
  • any reports your approval needs, such as bushfire, acoustic, flood, dilapidation, hydraulic or landscaping reports
  • generating your BASIX certificate
  • lodging your DA with council, or your CDC or Construction Certificate with a private certifier
  • meeting any approval conditions and water authority requirements before your building contract is signed

Whether you’re planning one of our home designs or a fully custom home, approvals are a big part of your overall timeline. Our article on how long it takes to build a house shows where they sit alongside the build itself.

FAQs

Frequently asked questions

Straight answers to the questions we hear most before a build begins.

Is a CDC the same as a DA?

No. A CDC is a combined planning and construction approval for projects that meet fixed state standards, issued by a certifier or council. A DA is a merit-based assessment by council, followed by a separate Construction Certificate.

Fees are set by each council and certifier, so there’s no single answer. A CDC’s shorter timeframe can help keep your overall project on schedule, but a DA may avoid design compromises that cost more in the long run.

Yes. If your site or design doesn’t meet the CDC standards, a DA is the alternative pathway, and council can consider variations to certain controls.

With a DA, you still need a Construction Certificate before work begins. With a CDC, you can start once a principal certifier is appointed and your neighbours have been given notice.

Yes. Every new home in NSW needs one. Alterations and additions worth $50,000 or more, and pools or spas holding 40,000 litres or more, also need a BASIX certificate.

Get the right approval pathway from the start

The right approval pathway depends on your land and the home you want to build, and making that call early saves time and redesigns. As part of our design and build service, we handle the entire approval process on your behalf, so you don’t have to navigate council requirements, paperwork and approvals on your own.

If you’re planning a new home or knockdown rebuild in Sydney or the Greater Sydney region, contact our team to talk through your block and the options available to you. 

About Us
BuildTec Homes

BuildTec Homes is a personalised, client-focused builder, creating homes that are thoughtfully designed, well-built and tailored to how you want to live. We take on a limited number of projects each year, so we stay closely involved throughout your entire build. Want to learn more about how BuildTec Homes can help build your dream home?